For Written Answer on : 18/05/2023
Question Number(s): 255 Question Reference(s): 23939/23
Department: Education
Asked by: David Stanton T.D.
______________________________________________


QUESTION


To ask the Minister for Education if she will provide an update on the progress of a school build (details supplied); when she expects the school to be open; and if she will make a statement on the matter.

(Details Supplied) Carrigtwohill Schools Campus (Scoil Mhuire Naofa, Scoil Chliodhna and Carrigtwohill Community College), Carrigtwohill, Co. Cork.

REPLY


The Letter of Acceptance (LOA) for the schools referred to by the Deputy issued to the preferred tenderer on the 31st May 2022 commencing the school building contract.

Works are progressing well on site and the school buildings are due for completion in Q4 2023.

My Department has been liaising with the patron bodies of the schools referred to by the Deputy in relation to interim accommodation requirements pending completion of the permanent accommodation for the schools.